Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 2.5 | 2.5 | 0 |
47W276 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0स0 1836/।।।(2)/18-10(एम.एल.ए.)/2016 दि0 13.07.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 52.15 Lacs
Resanction Cost : 52.15 Lacs
Exp. Upto Last Fy : 1.25 Lacs
For CFY 2024-2025
Remaining : 50.90 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.25 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 10 months ago
13 Jul 2016
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य द्वितीय चरण में स्वीकृत हो चुका है। -- as on 12-Feb-2024
Physical Peramenters