Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 2.5 | 2.5 | 0 |
47W276 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0स0 1836/।।।(2)/18-10(एम.एल.ए.)/2016 दि0 13.07.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
52.15
Resanction Cost :
52.15
Tentative Cost :
52.15
Exp. Upto Last Fy : 1.25
For CFY 2024-2025
Remaining : 50.90
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.25
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 years 4 days ago
13 Jul 2016
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य द्वितीय चरण में स्वीकृत हो चुका है। -- as on 12-Feb-2024
Physical Peramenters