Work Profile Report [47W300]

वीरखाल से बरसीला होते हुये ग्राम पंचायत मंजुली तक मोटर मार्ग का निर्माण (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : श्शा0सं0 2331/।।।(2)/16-10(एम.एल.ए.)/2016 दि0 17.08.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

27.10

Resanction Cost :

27.10

Tentative Cost :

27.10

Exp. Upto Last Fy :

6.43

For CFY 2025-2026

Remaining :

20.67

Demand :

7.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

6.43

Alignment Approved

Sanction on : 8 years 7 months ago

17 Aug 2016

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

80 %

Tentative Completion date on : 2 months 3 weeks from now

30 Jun 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
5
4
0.000
4
4.000
0.000

Remark

view all

वनभूमि हस्तान्तरण की विधिवत स्वीकृति प्राप्त। मार्ग पी0एम0जी0एस0वाई को हस्तान्तरित। प्रतिकर वितरित किया जा रहा है। -- as on 27-Mar-2025

Rating : 85

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: