Work Profile Report [47W332]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 382/।।।(2)/17-10(एम0एल0ए0)/2017 दिनंाक 01.08.2017
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8.04
Resanction Cost :
8.04
Tentative Cost :
8.04
Exp. Upto Last Fy :
4.22
For CFY 2025-2026
Remaining :
3.82
Demand :
3.82
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
4.22
Alignment Approved
Sanction on : 7 years 8 months ago
01 Aug 2017
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
50 %
Tentative Completion date on : 11 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वनभूमि प्रस्ताव नोड़ल अधिकारी स्तर पर लम्बित है। -- as on 27-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: