Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 12 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 24 | 24 | 24 | 0 |
47W357 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 5221/।।।(2)/18-10(एम0एल0ए0)/2017 टी0सी0 दिनांक 23.10.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 40.56 Lacs
Resanction Cost : 40.56 Lacs
Exp. Upto Last Fy : 2.47 Lacs
For CFY 2024-2025
Remaining : 38.09 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.47 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 6 months ago
23 Oct 2018
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
प्रस्ताव आॅनलाइन किया जा चुका है। प्रस्ताव आपत्तियों में इस खण्ड़ को वापस किया गया है। जिसके निराकरण की कार्यवाही गतिमान है। -- as on 23-Dec-2023
Physical Peramenters