Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
47W395 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेष सं0 4298/।।।(2)/19-10(एम0एल0ए0)/2017 टी0सी0 दिनांक 27.11.2019
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 16.08 Lacs
Resanction Cost : 16.08 Lacs
Exp. Upto Last Fy : 5.95 Lacs
For CFY 2024-2025
Remaining : 10.13 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 5.95 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 years 5 months ago
27 Nov 2019
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 12: AIP DM
Bottelneck: no issue
एन0पी0वी0 एवं क्षतिपूरक वृक्षारोपण की धनराशि वन विभाग के पक्ष में दिनंाक 08.09.2023 जमा की जा चुकी है। हस्तान्तरण नामान्तरण की कार्यवाही गतिमान है। -- as on 03-May-2024
Physical Peramenters