Work Profile Report [47W395]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेष सं0 4298/।।।(2)/19-10(एम0एल0ए0)/2017 टी0सी0 दिनांक 27.11.2019
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
16.08
Resanction Cost :
16.08
Tentative Cost :
16.08
Exp. Upto Last Fy :
5.95
For CFY 2024-2025
Remaining :
10.13
Demand :
3.50
Allotment :
7.00
Exp in CFY :
7.00
Total Up to Date Exp :
12.95
Alignment Approved
Sanction on : 5 years 4 weeks ago
27 Nov 2019
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
60 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रकरण उपजिलाधिकारी स्तर पर दाखिल खारिज हेतु लम्बित है। -- as on 24-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand