Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
47W395 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेष सं0 4298/।।।(2)/19-10(एम0एल0ए0)/2017 टी0सी0 दिनांक 27.11.2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
16.08
Resanction Cost :
16.08
Tentative Cost :
16.08
Exp. Upto Last Fy : 5.95
For CFY 2024-2025
Remaining : 10.13
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 5.95
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
4 years 7 months ago
27 Nov 2019
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 12: AIP DM
Bottelneck: no issue
उक्त मार्ग के क्षतिपूरक वृक्षारोपण के हस्तान्तरण नामान्तरण की कार्यवाही हेतु जिलाधिकारी महोदय को इस कार्यालय के पत्रांक 854/33सी0 दिनांक 22.05.2024 द्वारा पत्र प्रेषित किया गया है। 14-Jun -- as on 15-Jul-2024
Physical Peramenters