Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 1.000 | 0.000 |
47W531 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 -2620(1)/।।।(2)/21-10(एम0एल0ए0)/2017 टी0सी0-।।। दिनांक 31.03.2022
TS Amount (lakhs) : 111.41 Lacs
Financial Detail
Sanction Cost : 111.41 Lacs
Resanction Cost : 111.41 Lacs
Exp. Upto Last Fy : 79.69 Lacs
For CFY 2024-2025
Remaining : 31.72 Lacs
Demand : 20.00 Lacs
Allotment : 5.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 79.69 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कि0मी0 5.00 में ग्रामीण कुूनड़ी के ग्रामवासियों द्वारा विवाद किया जा रहा है, जिसे सुलझाने का प्रयास किया जा रहा है। दिनांक 17.01.2024 को ग्रामसभा कुनड़ी के ग्रामीण के साथ बैठक की गई है दिनांक 16.02.2024 को ग्राम बड़कोट के ग्रामीणों के साथ बैठक की गई, दिनांक 25.02.2024 को ग्रामीण बुड़कोट के ग्रामीणों द्वारा आपसी बैठक के उपरान्त इस पर सहमति हो पायेगी तत्पश्चात कार्य पुनः प्रारम्भ किया जायेगा। -- as on 15-May-2024
Physical Peramenters