Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 1.000 | 0.000 |
47W531 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 -2620(1)/।।।(2)/21-10(एम0एल0ए0)/2017 टी0सी0-।।। दिनांक 31.03.2022
TS Amount (lakhs) : 111.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
111.41
Resanction Cost :
111.41
Tentative Cost :
111.41
Exp. Upto Last Fy : 79.69
For CFY 2024-2025
Remaining : 31.72
Demand : 23.36
Allotment : 9.50
Exp in CFY : 9.05
Total Up to Date Exp : 88.75
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कि0मी0 5.00 में ग्रामीण कुूनड़ी के ग्रामवासियों द्वारा विवाद किया जा रहा है, जिसे सुलझाने का प्रयास किया जा रहा है। दिनांक 17.01.2024 को ग्रामसभा कुनड़ी के ग्रामीण के साथ बैठक की गई है दिनांक 16.02.2024 को ग्राम बड़कोट के ग्रामीणों के साथ बैठक की गई, दिनांक 25.02.2024 को ग्रामीण बुड़कोट के ग्रामीणों द्वारा आपसी बैठक के उपरान्त इस पर सहमति हो पायेगी तत्पश्चात कार्य पुनः प्रारम्भ किया सकेगा 0.500 कि0मी0 तक सहमति प्राप्त हुई, जो कि कट चुकी है शेष लम्बाई में विवाद सुलझाया जा रहा है। -- as on 10-Jun-2024
Physical Peramenters