Administrative Approval Detail : E-File-49188 Dt- 25-09-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6.00
Resanction Cost :
6.00
Tentative Cost :
6.00
Exp. Upto Last Fy :
0.17
For CFY 2024-2025
Remaining :
5.83
Demand :
1.00
Allotment :
0.50
Exp in CFY :
0.46
Total Up to Date Exp :
0.62
Alignment Approved
Sanction on : 1 year 2 months ago
25 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
15 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अधीक्षण अभियन्ता 8वां वृत्त लो0नि0वि0 टिहरी के पत्रांक 3563/909सी0-8/2023 दिनांक 21.092024 द्वारा समरेखण अनुमोदित। डी0पी0आर0 गठित की जा रही है। -- as on 22-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand