Work Profile Report [47W592]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E-File-39499 Dt- 02-08-2023
TS Amount (lakhs) : 172.35 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
172.35
Resanction Cost :
172.35
Tentative Cost :
172.35
Exp. Upto Last Fy :
0.76
For CFY 2024-2025
Remaining :
171.59
Demand :
75.00
Allotment :
125.10
Exp in CFY :
73.68
Total Up to Date Exp :
74.44
Construction Started
Sanction on : 1 year 3 months ago
02 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
60 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.00 कि0मी0 में पहाड़ कटान कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 08-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand