Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.05 | 5.05 | 0.000 | 5.05 | 2.550 | 0.000 |
47W604 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-39499/10 Dt- 07-02-2024
TS Amount (lakhs) : 180.05 Lacs
Financial Detail
Sanction Cost : 180.05 Lacs
Resanction Cost : 180.05 Lacs
Exp. Upto Last Fy : 52.56 Lacs
For CFY 2024-2025
Remaining : 127.49 Lacs
Demand : 70.00 Lacs
Allotment : 5.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 52.56 Lacs
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 months 1 week ago
07 Feb 2024
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य की निविदा प्राप्त , अनुबन्ध गठन की कार्यवाही प्रगति पर है। -- as on 10-Mar-2024
Physical Peramenters