Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.05 | 5.05 | 0.000 | 5.05 | 2.550 | 0.000 |
47W604 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-39499/10 Dt- 07-02-2024
TS Amount (lakhs) : 180.05 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
180.05
Resanction Cost :
180.05
Tentative Cost :
180.05
Exp. Upto Last Fy : 52.56
For CFY 2024-2025
Remaining : 127.49
Demand : 70.00
Allotment : 15.07
Exp in CFY : 6.85
Total Up to Date Exp : 59.41
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 months 1 week ago
07 Feb 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.50 कि0मी0 में पहाड़ कटान का कार्य पूर्ण शेष कार्य प्रगति पर है। -- as on 15-Jul-2024