Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 3.500 | 0.5 | 0.500 | 0.000 |
49W203 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1868/।।।(2)/16-19(प्रा0आ0)/2016 दिनाॅक-7 जून 2016
TS Amount (lakhs) : 258 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
258.00
Resanction Cost :
258.00
Tentative Cost :
258.00
Exp. Upto Last Fy : 142.03
For CFY 2024-2025
Remaining : 115.97
Demand : 70.00
Allotment : 23.00
Exp in CFY : 0.00
Total Up to Date Exp : 142.03
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 65 %
Sanction on :
8 years 1 month ago
07 Jun 2016
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का कार्य 4.00 कि0मी0 तक अधिंकाश रूप से करा लिया गया हैै। कतिपय स्थानों डिफेक्ट कटिंग का कार्य गतिमान है। पार्ट-2 का कार्य 3.5 कि0मी0 तक पूर्ण,शेष कार्य प्रगति पर। -- as on 06-Feb-2023
Physical Peramenters