Work Profile Report [49W208]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0-1869/।।।(2)/16-19(प्रा0आ0)/2016 दिनाॅक-07.06.2016
TS Amount (lakhs) : 47.2 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.20
Resanction Cost :
47.20
Tentative Cost :
47.20
Exp. Upto Last Fy :
1.26
For CFY 2025-2026
Remaining :
45.94
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.26
Alignment Approved
Sanction on : 9 years 3 weeks ago
07 Jun 2016
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 8 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वन विभाग से पेड़ो की गणना की आख्या प्राप्त होने के उपरांत वनभूमि हस्तांतरण प्रस्ताव गठित किया जायेगा | -- as on 02-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: