Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 21.43 | 21.43 | 13.000 | 8.43 | 5.000 | 0.000 |
49W388 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ष्शा0 सं0 557(1)/।।।(2)/20-25 (प्रा0आ0)/2017, दि0 05.02.2020
TS Amount (lakhs) : 1007.07 Lacs
Financial Detail
Sanction Cost : 1,007.07 Lacs
Resanction Cost : 1,007.07 Lacs
Exp. Upto Last Fy : 859.32 Lacs
For CFY 2024-2025
Remaining : 147.75 Lacs
Demand : 40.71 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 859.32 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 86 %
Up to Date : 86 %
Sanction on :
4 years 3 months ago
05 Feb 2020
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पूर्व में स्वीकृत हल्का वाहन मार्ग का मोटर मार्ग में परिवर्तन का कार्य विलम्ब से दिनांक 13.06.2021 को पूर्ण हुआ जबकि अनुबन्ध के अनुसार कार्य समाप्ति की तिथि 11.03.2021 थी। ठेकेदार मैं0 शिवालिक इन्फ्रावेन्चर लिमि0 को हल्का वाहन से मोटर मार्ग में परिवर्तन का कार्य विलम्ब से करने हेतु अर्थदण्ड भी लगाया गया है। दिनांक 13.06.2021 के पश्चात ही उक्त मोटर मार्ग का कार्य प्रारम्भ किया गया, जिसके बाद मानसून 2021 की अवधि में भी कार्य करने में विलम्ब हुआ तथा वर्ष 2022, 2023 में कि0मी0 14,15,16 में मार्ग कई स्थानों पर वासआउट होने के कारण कार्य बाधित हुआ है तथा उक्त कि0मी0 में क्रोनिक स्लाईड जोन बन जाने के कारण कार्य में विलम्ब हो रहा हैं। मौसम अनुकूल न होने के कारण डामरीकरण का कार्य बाधित रहा।
वर्तमान में जी0-1 जी0-2, जी-3 का कार्य पूर्ण व पी0सी0 का कार्य 13.00 किमी0 तक पूर्ण शेष कार्य प्रगति पर। मुख्य अभियन्ता, लो0नि0वि0, पौडी महोदय द्वारा भी अपने निरीक्षण आख्या में दिनांक 30.06.2024 तक कार्य पूर्ण करने हेतु निर्देश दिये गये है। दिनांक 30.06.2024 तक कार्य पूर्ण कर लिया जायेगा।
-- as on 07-Mar-2024
Physical Peramenters