Work Profile Report [49W643]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन का ई-पत्रांक:- 75508/14 दिनांक 27 मार्च, 2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
109.17
Resanction Cost :
109.17
Tentative Cost :
109.17
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
109.07
Demand :
40.00
Allotment :
21.13
Exp in CFY :
21.13
Total Up to Date Exp :
21.23
Construction Started
Sanction on : 4 months 1 week ago
27 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
1 %
Tentative Completion date on : 9 months 1 week from now
18 May 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सोलिंग कोट का कार्य लक्षित 5.00 किमी० लम्बाई के सापेक्ष 1.50 किमी० लम्बाई मे पूर्ण | अवशेष लम्बाई हेतु कार्य प्रगति पर | -- as on 29-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: