Work Profile Report [4W159]

जनपद अल्मोड़ा में हैड़ाखान से दाड़मी-बाधण मोटर मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

  • alerts
  • Documents

    Samples

Administrative Approval Detail : शासनादेश सं. 853/ 111 (2)/ 09-06(मु.मं.घा)/08टी.सी.दि0 2.3.09

TS Amount (lakhs) : 70 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

70.00

Resanction Cost :

70.00

Tentative Cost :

70.00

Exp. Upto Last Fy :

62.70

For CFY 2024-2025

Remaining :

7.30

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

62.70

Work completed

Sanction on : 15 years 9 months ago

02 Mar 2009

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 2 years 8 months ago

31 Mar 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
2
1.5
1.500
0
0.000
0.000

Remark

view all

कार्य पूर्ण। दायित्व शेष। क्षतिपूरक वृक्षारोपण हेतु उपलब्ध करायी गयी भूमि का अमलदरामद कराने हेतु इस कार्यालय के पत्रांक 2403/18सी. दिनांक 08.11.2024 को जिलाधिकारी, अल्मोड़ा को पत्र प्रेषित। -- as on 18-Nov-2024

Rating : 100

Forest Case Pending At : 12: AIP DM

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: