Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6.000 | 0 | 0.000 | 0.000 |
4W33 :
Work not linked with IM
Bridges on The Basis of AI: unknown bridge
Administrative Approval Detail : शासनादेश सं. 853/ 111 (2)/ 09-06(मु.मं.घा)/08टी.सी.दि0 02.03.2009 & E file no 33425/I/103249/2023 दि0 01.03.2023
TS Amount (lakhs) : 557.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
210.00
Resanction Cost :
347.91
Tentative Cost :
347.91
Exp. Upto Last Fy : 206.98
For CFY 2024-2025
Remaining : 140.93
Demand : 20.00
Allotment : 20.00
Exp in CFY : 0.00
Total Up to Date Exp : 206.98
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 100 %
Sanction on :
15 years 4 months ago
02 Mar 2009
Tentative Completion date:
3 weeks 2 days ago
24 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
पूर्व में उक्त मोटर मार्ग की स्वीकृति राज्य योजना के अन्तर्गत 6 किमी. हेतु रू. 210.00 लाख की प्राप्त थी जिसके सापेक्ष 3.50 किमी. में ही पहाड़ कटान व पार्ट-2 का कार्य पूर्ण कर लिया गया था। जिसमें निविदा कम दरों में प्राप्त होने के कारण व्यय रू. 119.50 लाख हुआ। अवशेष 2.50 किमी. हेतु पुनरीक्षित आगणन की स्वीकृति रू. 137.91 लाख की प्राप्त हुई। उक्त के सापेक्ष निविदा कम दरों में प्राप्त होने के कारण रू. 95.98 लाख का अनुबन्ध गठित किया गया। कार्य पूर्ण। दायित्व शेष। जिसमें लगभग रू. 84.76 लाख का व्यय किया जा चुका हेै एवं कार्य / अनुबन्ध की बचत की धनराशि लगभग रू. 120.00 लाख समर्पित की जानी है। जिस कारण वित्तीय वर्ष में मांग रू. 20.00 लाख की गयी है। विधिवत स्वीकृति प्राप्त किये जाने हेतु इस कार्यालय के पत्रांक 1024/18सी. दिनांक 27.04.2024 द्वारा नोडल अधिकारी, देहरादून से पुनः अनुरोध किया गया है। -- as on 04-Jul-2024
Physical Peramenters