Work Profile Report [4W449]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं. 428/111(2)/16-14(मु0मं0घो0)/ 2015 दिनांक 23.1.2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
32.22
Resanction Cost :
32.22
Tentative Cost :
1.16
Saving
31.06
Exp. Upto Last Fy :
0.16
For CFY 2025-2026
Remaining :
32.06
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.16
Alignment Approved
Sanction on : 9 years 11 months ago
23 Jan 2016
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 4 weeks 6 hours from now
31 Jan 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 31.06 has been recorded as expected cost of work reduced from 32.22 to 1.16 . -- as on 18-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: