Work Profile Report [4W535]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं. 8120/111(2)/18-48(एम.एल.ए.)/2017 टी.सी.-1 दिनांक 31.12.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
24.92
Resanction Cost :
24.92
Tentative Cost :
2.05
Saving
22.87
Exp. Upto Last Fy :
1.05
For CFY 2025-2026
Remaining :
23.87
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.05
Construction Started
Sanction on : 7 years 2 days ago
31 Dec 2018
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 1 year 1 week from now
15 Jan 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 22.87 has been recorded as expected cost of work reduced from 24.92 to 2.05 .
पुनः इस कार्यालय के पत्रांक 2118/18सी0, दिनांक 02.12.2025 द्वारा जिलाधिकारी, अल्मोड़़ा को क्षतिपूरक वृक्षारोपण हेतु पत्र प्रेषित। वन भूमि हस्तान्तरण हेतु सी0ए0 लैण्ड उपलब्ध न होने के कारण बचत हुई है।
-- as on 30-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand