Work Profile Report [4W541]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं. 269/111(2) /19-48(एम.एल.ए.)/2017 टी.सी.-1 दिनांक 22.1.2019
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.84
Resanction Cost :
3.84
Tentative Cost :
0.60
Saving
3.24
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
3.74
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Construction Started
Sanction on : 6 years 11 months ago
22 Jan 2019
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 2 months 1 week from now
15 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 3.24 has been recorded as expected cost of work reduced from 3.84 to 0.60 . -- as on 18-Dec-2025
Assets :
Work not linked with IM