Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.25 | 8.25 | 8.250 | 0 | 0.000 | 0.000 |
4W568 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं. 266/(1)111(2)/20-41(प्रा.आ.)/2006 दिनांक 10.01.2020
TS Amount (lakhs) : 664.72 Lacs
Financial Detail
Sanction Cost : 664.72 Lacs
Resanction Cost : 664.72 Lacs
Exp. Upto Last Fy : 478.97 Lacs
For CFY 2024-2025
Remaining : 185.75 Lacs
Demand : 80.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 478.97 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 4 months ago
10 Jan 2020
Tentative Completion date:
6 months 2 weeks ago
02 Nov 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। कार्य पूर्ण किये जाने में विलम्ब हेतु अनुबन्ध की शर्तानुसार ठेकेदार पर एल0डी0 आरोपित की गयी है। क्वालिटी माॅनीटर महोदय की परीक्षण रिपोर्ट की अनुपालन में सुधारात्मक कार्य कराये जा रहे है, पुनः निरीक्षण उपरान्त अनुबन्ध का अन्तिमीकरण कर लिया जायेगा, अवशेष दायित्वों के व्यय वहन हेतु, निविदा कम दरों पर प्राप्त होने के सापेक्ष रू. 80.00 लाख की ही मांग की गयी हेै। -- as on 13-May-2024
Physical Peramenters