Work Profile Report [4W621]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं. 436/111(2)/2021-48 (एम.एल.ए)/2017 टी.सी. दिनांक 06.01.2022
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
258.75
Resanction Cost :
258.75
Tentative Cost :
250.00
Saving
8.75
Exp. Upto Last Fy :
140.28
For CFY 2024-2025
Remaining :
118.47
Demand :
118.00
Allotment :
90.34
Exp in CFY :
48.09
Total Up to Date Exp :
188.37
In Maintenance After Completion
Sanction on : 2 years 10 months ago
06 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
100 %
Tentative Completion date on : 1 week 1 day ago
15 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 8.75 has been recorded as expected cost of work reduced from 258.75 to 250.00 .
1-4.00 किमी0 में सोलिंग इन्टर टाॅप एवं पी0सी0 का कार्य पूर्ण। 4.00 किमी0 में कल्वर्ट का कार्य पूर्ण। अनुबन्ध के अनुसार कार्य प्रारम्भ की तिथि 24.04.2023 एवं कार्य पूर्ण करने की तिथि 23.07.2024 थी । कार्य पूर्ण। दायित्व शेष।
2- अनुरक्षण रू. 6.70 लाख।
-- as on 21-Nov-2024