Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
51W1119 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 707/2021-01 (44)/2019
TS Amount (lakhs) : 612.76 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
857.20
Resanction Cost :
2482.96
Tentative Cost :
2482.96
Exp. Upto Last Fy : 1,193.24
For CFY 2024-2025
Remaining : 1,289.72
Demand : 1,289.73
Allotment : 171.28
Exp in CFY : 171.28
Total Up to Date Exp : 1,364.52
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 85 %
Sanction on :
2 years 8 months ago
01 Nov 2021
Tentative Completion date:
4 months 4 weeks from now
15 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर । -- as on 24-Jan-2024
Physical Peramenters