Work Profile Report [51W1166]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E-Letter no 27631 Dt. 31.3.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
12.96
Resanction Cost :
12.96
Tentative Cost :
12.96
Exp. Upto Last Fy :
4.80
For CFY 2025-2026
Remaining :
8.16
Demand :
0.05
Allotment :
0.05
Exp in CFY :
0.05
Total Up to Date Exp :
4.85
Unstarted Work
Sanction on : 2 years 9 months ago
31 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 2 months 3 weeks from now
30 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ई.डी0पी0आर0 गठित की जानी है। -- as on 27-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: