Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
51W1194 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Letter No 1081/XVIII B-1/2023-4/(70)/2023 Disaster Managerment Department Dt. 09.08.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2174.92
Resanction Cost :
2174.92
Tentative Cost :
2174.92
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 2,174.92
Demand : 1,500.00
Allotment : 500.00
Exp in CFY : 135.02
Total Up to Date Exp : 135.02
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
11 months 1 week ago
09 Aug 2023
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
कार्य का अनुबंध गठित है | पूर्व स्वीकृत DPR के प्रविधानों मे शासन द्वारा नियुक्त PMC (ULMMC) द्वारा वर्तमान मे Site specific conditions के अनुसार परिवर्तन कराए जाने के कारण संशोधित डिजाइन/डी.पी.आर. गठित की जा रही है PMC द्वारा टॉप स्टेज के लिए उपलब्ध कराई गई ड्रॉइंग के अनुसार दिनांक 25.04.2024 से कार्य प्रारंभ किया जा चुका है तथा अधतन टॉप बैंच पर SDA का लगभग 75% कार्य किया जा चुका है तथा Over all 10% प्रगति हो चुकी है | कार्य को माह दिसम्बर 2024 तक पूर्ण किए जाने का लक्ष्य रखा गया है | -- as on 12-Jun-2024
Physical Peramenters