Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.000 | 0.5 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 45 | 45 | 0.000 | 45 | 0.000 | 0.000 |
51W1199 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E Letter No 37290 Dt. 09.11.2022
TS Amount (lakhs) : 12.45 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
12.45
Resanction Cost :
12.45
Tentative Cost :
12.45
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 12.45
Demand : 10.00
Allotment : 0.00
Exp in CFY : 3.90
Total Up to Date Exp : 3.90
Survey work done
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
1 year 8 months ago
09 Nov 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
भूस्वामी की सहमति के पश्चात सेतु का एप्रोच रोड सहित सर्वे कार्य पूर्ण। सेतु स्थल चयन आख्या अधी0अभि0 के पत्रांक 7718/02सी-9/23 दि0 14.11.2023 द्वारा स्वीकृत डीपीआर गठन हेतु अनुबन्ध गठित।DPR गठन की कार्यवाही की जा रही है। -- as on 04-Apr-2024
Physical Peramenters