Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.4 | 1.4 | 0.000 | 1.4 | 1.400 | 0.000 |
51W1204 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E Letter No 47325 Dt. 29.08.2023
TS Amount (lakhs) : 520.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
520.50
Resanction Cost :
520.50
Tentative Cost :
520.50
Exp. Upto Last Fy : 207.66
For CFY 2024-2025
Remaining : 312.84
Demand : 40.00
Allotment : 0.00
Exp in CFY : 0.24
Total Up to Date Exp : 207.90
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 25 %
Sanction on :
10 months 2 weeks ago
29 Aug 2023
Tentative Completion date:
4 months 3 weeks from now
10 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 04-Apr-2024
Physical Peramenters