Work Profile Report [51W1218]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E letter No 34340 Dt. 12.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
7.73
Resanction Cost :
7.73
Tentative Cost :
7.73
Exp. Upto Last Fy :
0.36
For CFY 2024-2025
Remaining :
7.37
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.36
Survey work done
Sanction on : 1 year 2 months ago
12 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
50 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सर्वेक्षण कार्य पूर्ण। संमेरखण प्रस्ताव गठन का कार्य प्रगति में है। -- as on 04-Jan-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand