Work Profile Report [51W1340]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E - File No.56976 PWD Anubhag-2 Dehradun Dt. 11-9-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
143.40
Resanction Cost :
143.40
Tentative Cost :
143.40
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
143.40
Demand :
20.00
Allotment :
0.49
Exp in CFY :
0.49
Total Up to Date Exp :
0.49
Construction Started
Sanction on : 4 months 1 week ago
11 Sep 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
10 %
Tentative Completion date on : 4 months 2 days from now
26 May 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
work in progress -- as on 12-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: