Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 0.000 | 3.5 | 0.000 | 0.000 |
52W32 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2658/111-2/06-17 (प्रा0आ0)/06 दि0 25.09.2006
TS Amount (lakhs) : 147.56 Lacs
Financial Detail
Sanction Cost : 56.70 Lacs
Resanction Cost : 73.78 Lacs
Exp. Upto Last Fy : 62.67 Lacs
For CFY 2024-2025
Remaining : 11.11 Lacs
Demand : 7.21 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 62.67 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
17 years 7 months ago
25 Sep 2006
Tentative Completion date:
2 months 2 weeks ago
03 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
पहाड़ कटान का 3.50 कि.मी. कार्य पूर्ण, दायित्वों का भुगतान शेष। -- as on 07-Mar-2024