Work Profile

52W32 :

No Pic Avilable Time series Gantt
सारनी मोटर मार्ग का विस्तार।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0सं0-2658/111-2/06-17 (प्रा0आ0)/06 दि0 25.09.2006

TS Amount (lakhs) : 147.56 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

56.70

Resanction Cost :

73.78

Tentative Cost :

73.78

Exp. Upto Last Fy : 62.67

For CFY 2024-2025

Remaining : 11.11

Demand : 7.21

Allotment : 4.00

Exp in CFY : 3.90

Total Up to Date Exp : 66.58

Construction Started

Physical Progress:

At start of FY 2024-2025 : 90 %

Up to Date : 90 %

Sanction on :
17 years 9 months ago
25 Sep 2006


Tentative Completion date:
1 month 2 weeks from now
03 Sep 2024


Actual Completion Date:
Not Yet Reported


Rating : 92

Remark

Forest Status 21: Final

Bottelneck: no issue


पहाड़ कटान का 3.50 कि.मी. कार्य पूर्ण, दायित्वों का भुगतान शेष। -- as on 07-Mar-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 3.5 3.5 0.000 3.5 0.000 0.000
Currently only Bank Gaurantee information is avilable