Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 0.000 | 3.5 | 0.000 | 0.000 |
52W32 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2658/111-2/06-17 (प्रा0आ0)/06 दि0 25.09.2006
TS Amount (lakhs) : 147.56 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
56.70
Resanction Cost :
73.78
Tentative Cost :
73.78
Exp. Upto Last Fy : 62.67
For CFY 2024-2025
Remaining : 11.11
Demand : 7.21
Allotment : 4.00
Exp in CFY : 3.90
Total Up to Date Exp : 66.58
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
17 years 9 months ago
25 Sep 2006
Tentative Completion date:
1 month 2 weeks from now
03 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
पहाड़ कटान का 3.50 कि.मी. कार्य पूर्ण, दायित्वों का भुगतान शेष। -- as on 07-Mar-2024
Physical Peramenters