Work Profile Report [52W32]

सारनी मोटर मार्ग का विस्तार।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0-2658/111-2/06-17 (प्रा0आ0)/06 दि0 25.09.2006

TS Amount (lakhs) : 147.56 Lacs

Budget Financial Head : TSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

56.70

Resanction Cost :

73.78

Tentative Cost :

73.78

Exp. Upto Last Fy :

62.67

For CFY 2024-2025

Remaining :

11.11

Demand :

4.00

Allotment :

5.42

Exp in CFY :

5.42

Total Up to Date Exp :

68.10

Construction Started

Sanction on : 18 years 2 months ago

25 Sep 2006

Physical Progress:

At start of FY 2024-2025 :

90 %

Up to Date :

90 %

Tentative Completion date on : 1 month 6 days from now

31 Jan 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3.5
3.5
0.000
3.5
0.000
0.000

Remark

view all

पहाड़ कटान का 3.50 कि.मी. कार्य माह 05/2023 को पूर्ण, प्रतिकर पत्रावली गठित कर अनुुमोदन पश्चात प्रतिकर वितरण कर दिया जायेगा। -- as on 08-Oct-2024

Rating : 93

Forest Case Pending At : 21: Final

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand