Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
52W388 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-1297/।।।(2)/20-30(प्रा0आ.)/ 2017 दिनांक 14.07.2020
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
23.38
Resanction Cost :
23.38
Tentative Cost :
23.38
Exp. Upto Last Fy : 1.72
For CFY 2024-2025
Remaining : 21.66
Demand : 21.66
Allotment : 4.33
Exp in CFY : 0.00
Total Up to Date Exp : 1.72
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 3 days ago
14 Jul 2020
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण, द्वितीय चरण स्टेज-।,की स्वीकृति शा0सं0-ई पत्रावली संख्या-45425 ,लोक निर्माण अनुभाग-2,देहरादून दिनांक 24 जुलाई 2023 द्वारा रू0 140.76 लाख की प्राप्त। मुआवजा वितरण हेतु पत्रावली गठित करने की कार्यवाही की जा रही है। -- as on 27-Apr-2024
Physical Peramenters