Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
52W454 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली संख्या-30723 लोक निर्माण अनुभा-देहरादून दिनांक 24 जनवरी 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.50
Resanction Cost :
4.50
Tentative Cost :
4.50
Exp. Upto Last Fy : 0.07
For CFY 2024-2025
Remaining : 4.43
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.07
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 5 months ago
24 Jan 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण कार्य पूर्ण, तथा समरेखण प्रस्ताव दिनांक 31.08.2024 तक प्रेषित कर दिया जाएगा । -- as on 15-Jul-2024
Physical Peramenters