Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.2 | 2.2 | 0.000 | 2.2 | 2.200 | 0.000 |
52W457 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 ई पत्रावली संख्या-37518 अनुभाग-2, देहरादून दिनांक 22 मार्च 2023
TS Amount (lakhs) : 181.79 Lacs
Financial Detail
Sanction Cost : 181.79 Lacs
Resanction Cost : 195.03 Lacs
Exp. Upto Last Fy : 152.74 Lacs
For CFY 2024-2025
Remaining : 42.29 Lacs
Demand : 13.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 152.74 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 1 month ago
22 Mar 2023
Tentative Completion date:
1 month 3 weeks from now
11 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्कपर का निर्माण कार्य पूर्ण तथा जी.1जी2 का कार्य पूर्ण,व जी 3 का 2.20 Km कार्य पूर्ण, शेष फर्नीचर का कार्य प्रगति पर है। तथा पी0सी0 का कार्य प्रगति पर है। -- as on 07-Mar-2024