Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.2 | 2.2 | 0.000 | 2.2 | 2.200 | 2.200 |
52W457 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 ई पत्रावली संख्या-37518 अनुभाग-2, देहरादून दिनांक 22 मार्च 2023
TS Amount (lakhs) : 181.79 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
181.79
Resanction Cost :
195.03
Tentative Cost :
195.03
Exp. Upto Last Fy : 152.74
For CFY 2024-2025
Remaining : 42.29
Demand : 13.00
Allotment : 14.30
Exp in CFY : 6.87
Total Up to Date Exp : 159.62
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
22 Mar 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण ,दायित्वों का भुगतान हेतु कनिष्ठ अभियन्ता द्वारा अंतिम देयक प्रस्तुत किया जाना है। -- as on 04-Jul-2024
Physical Peramenters