Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 18 | 18 | 0.000 | 18 | 0.000 | 0.000 |
52W467 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 ई पत्रावली संख्या-48114 अनुभाग-2, देहरादून दिनांक 28.02.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 5.40 Lacs
Resanction Cost : 5.40 Lacs
Exp. Upto Last Fy : 2.89 Lacs
For CFY 2024-2025
Remaining : 2.51 Lacs
Demand : 0.72 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.89 Lacs
Phase1 DPR Submitted
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 52 %
Sanction on :
1 year 2 months ago
28 Feb 2023
Tentative Completion date:
5 months 1 day from now
21 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0पी0आर0 डिजाइन गठित कर डिजाइन सेल लोक निर्माण विभाग में जांच हेतु प्रेषित किया गया है | -- as on 01-May-2024
Physical Peramenters