Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 20 | 20 | 0.000 | 20 | 0.000 | 0.000 |
52W469 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 ई पत्रावली संख्या-48114 अनुभाग-2, देहरादून दिनांक 28.02.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
6.00
Resanction Cost :
6.00
Tentative Cost :
6.00
Exp. Upto Last Fy : 3.39
For CFY 2024-2025
Remaining : 2.61
Demand : 0.62
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 3.39
Phase1 DPR Submitted
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 56 %
Sanction on :
1 year 4 months ago
03 Mar 2023
Tentative Completion date:
3 months 3 days from now
21 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0पी0आर0/डिजाइन गठित कर डिजाइन सेल लोक निर्माण विभाग में जांच हेतु प्रेषित किया गया है | -- as on 12-Jul-2024
Physical Peramenters