Work Profile Report [53W1341]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 5726/।।।(2)/18-23(एम0एल0ए0)2017 टी0सी0 ।। दिनांक 29.11.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
13.80
Resanction Cost :
13.80
Tentative Cost :
13.80
Exp. Upto Last Fy :
0.08
For CFY 2024-2025
Remaining :
13.72
Demand :
1.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.08
Survey work done
Sanction on : 6 years 3 weeks ago
29 Nov 2018
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
10 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वन भूमि के प्रस्ताव आपत्तियों के निराकरण के उपरान्त दिनांक 03.06.2024 को वन भूमि के प्रस्ताव नोडल अधिकारी को प्रेषित। -- as on 04-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: