Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.6 | 1.6 | 0.000 | 1.6 | 0.000 | 0.000 |
53W1404 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 434/।।।(2)/20-23 (एम0एल0ए0)/2017 दिनांक 27.01.2020
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1.60
Resanction Cost :
1.60
Tentative Cost :
1.60
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 1.60
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Survey work done
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
4 years 5 months ago
27 Jan 2020
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
मार्ग पर वन विभाग एवं राजस्व विभाग द्वारा दिनांक 21.05.2024 को संयुक्त निरीक्षण किया जा चुका हैं। अग्रिम कार्यवाही की जा रही ह। -- as on 31-May-2024
Physical Peramenters