Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.8 | 0.8 | 0.000 | 0.8 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 30 | 30 | 0.000 | 30 | 0.000 | 0.000 |
53W1484 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 68/।।।(2)/21-23(एम.एल.ए.)2017 दिनांक 19.01.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 37.29 Lacs
Resanction Cost : 37.29 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 37.29 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
3 years 4 months ago
19 Jan 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
मार्ग के समरेखण पर ग्रामीणों द्वारा विवाद किया जा रहा है। -- as on 09-Aug-2021
Physical Peramenters