Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.8 | 0.8 | 0.000 | 0.8 | 0.000 | 0.000 |
53W1623 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन, देहरादून की ई पत्रावली संख्या 24012 दिनांक 16.01.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2.40
Resanction Cost :
2.40
Tentative Cost :
2.40
Exp. Upto Last Fy : 0.38
For CFY 2024-2025
Remaining : 2.02
Demand : 2.00
Allotment : 0.50
Exp in CFY : 0.07
Total Up to Date Exp : 0.44
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
1 year 6 months ago
16 Jan 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
मार्ग का समरेखण अधी0अभि0 के पत्रांक 2759/237 (88) सी-9/24 दिनांक 13.05.24 द्वारा स्वीकृत। वन भूमि के प्रस्ताव गठित कर हस्ताक्षर हेतु अधि0अभि0 के पत्रांक 918/वनभूमि दिनांक 08-07-2024 द्वारा प्रभागीय वनाधिकारी को प्रेषित किये गये है । -- as on 16-Jul-2024
Physical Peramenters