Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 25.225 | 25.575 | 7.500 | 18.075 | 12.800 | 0.000 |
53W1633 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन, देहरादून की ई पत्रावली संख्या 49284 दिनांक 29.03.2023
TS Amount (lakhs) : 694.87 Lacs
Financial Detail
Sanction Cost : 694.87 Lacs
Resanction Cost : 694.87 Lacs
Exp. Upto Last Fy : 109.51 Lacs
For CFY 2024-2025
Remaining : 585.36 Lacs
Demand : 300.00 Lacs
Allotment : 100.00 Lacs
Exp in CFY : 0.61 Lacs
Total Up to Date Exp : 110.12 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
1 year 1 month ago
29 Mar 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 02-Nov-2023
Physical Peramenters