Administrative Approval Detail : उत्तराखण्ड शासन, देहरादून की ई पत्रावली संख्या 49284 दिनांक 29.03.2023
TS Amount (lakhs) : 694.87 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
694.87
Resanction Cost :
694.87
Tentative Cost :
694.87
Exp. Upto Last Fy :
109.51
For CFY 2024-2025
Remaining :
585.36
Demand :
300.00
Allotment :
300.00
Exp in CFY :
261.71
Total Up to Date Exp :
371.22
Construction Started
Sanction on : 1 year 8 months ago
29 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
61 %
Tentative Completion date on : 3 months 1 week from now
02 Apr 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
बी0सी0, जी0एस0बी0, जी3 एवं इण्टरलाॅकिंग लगाये जाने का कार्य प्रगति पर है। -- as on 29-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: