Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 25.225 | 25.575 | 7.500 | 18.075 | 12.800 | 0.000 |
53W1633 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन, देहरादून की ई पत्रावली संख्या 49284 दिनांक 29.03.2023
TS Amount (lakhs) : 694.87 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
694.87
Resanction Cost :
694.87
Tentative Cost :
694.87
Exp. Upto Last Fy : 109.51
For CFY 2024-2025
Remaining : 585.36
Demand : 300.00
Allotment : 100.00
Exp in CFY : 143.99
Total Up to Date Exp : 253.50
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 46 %
Sanction on :
1 year 3 months ago
29 Mar 2023
Tentative Completion date:
8 months 2 weeks from now
02 Apr 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
बी0सी0, जी0एस0बी0, जी3 एवं इण्टरलाॅकिंग लगाये जाने का कार्य प्रगति पर है। -- as on 29-Jun-2024
Physical Peramenters