Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.25 | 3.75 | 0.000 | 3.75 | 3.750 | 2.000 |
53W1650 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 46690 दिनांक 28.06.2023
TS Amount (lakhs) : 232.69 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
232.69
Resanction Cost :
250.14
Tentative Cost :
250.14
Exp. Upto Last Fy : 106.29
For CFY 2024-2025
Remaining : 143.85
Demand : 126.00
Allotment : 126.00
Exp in CFY : 20.18
Total Up to Date Exp : 126.46
Construction Started
Physical Progress:
At start of FY 2024-2025 : 52 %
Up to Date : 95 %
Sanction on :
1 year 2 weeks ago
28 Jun 2023
Tentative Completion date:
3 months 1 week from now
29 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग पर पी0सी0 का कार्य माह 06/2024 में पूर्ण। नाली पटरी आदि का कार्य प्रगति पर है। -- as on 03-Jul-2024
Physical Peramenters