Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.25 | 3.75 | 0.000 | 3.75 | 3.750 | 0.000 |
53W1650 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 46690 दिनांक 28.06.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 232.69 Lacs
Resanction Cost : 250.14 Lacs
Exp. Upto Last Fy : 106.29 Lacs
For CFY 2024-2025
Remaining : 143.85 Lacs
Demand : 126.00 Lacs
Allotment : 24.00 Lacs
Exp in CFY : 0.34 Lacs
Total Up to Date Exp : 106.62 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 52 %
Up to Date : 52 %
Sanction on :
10 months 3 weeks ago
28 Jun 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग पर टाप कोट का कार्य प्रगति पर है। -- as on 01-May-2024
Physical Peramenters