Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.225 | 4.225 | 0.000 | 4.225 | 2.000 | 0.000 |
53W1686 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 46690 दिनांक 30.10.2023
TS Amount (lakhs) : 215.51 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
256.11
Resanction Cost :
256.11
Tentative Cost :
256.11
Exp. Upto Last Fy : 0.15
For CFY 2024-2025
Remaining : 255.96
Demand : 150.00
Allotment : 50.00
Exp in CFY : 2.60
Total Up to Date Exp : 2.75
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 3 %
Sanction on :
8 months 2 weeks ago
30 Oct 2023
Tentative Completion date:
1 year 3 weeks from now
13 Aug 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग पर डेªसिंग आदि का कार्य प्रगति पर है। -- as on 01-May-2024
Physical Peramenters