Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 0.000 |
53W1688 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 24012 दिनांक 25.09.2023
TS Amount (lakhs) : 112.74 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
112.74
Resanction Cost :
112.74
Tentative Cost :
112.74
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 112.74
Demand : 100.00
Allotment : 50.00
Exp in CFY : 15.27
Total Up to Date Exp : 15.27
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
9 months 3 weeks ago
25 Sep 2023
Tentative Completion date:
1 year 3 weeks from now
13 Aug 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग पर जी1 का कार्य प्रगति पर है। -- as on 30-Jun-2024
Physical Peramenters