Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 0.000 |
53W1688 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 24012 दिनांक 25.09.2023
TS Amount (lakhs) : 112.74 Lacs
Financial Detail
Sanction Cost : 112.74 Lacs
Resanction Cost : 112.74 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 112.74 Lacs
Demand : 100.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
7 months 3 weeks ago
25 Sep 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग पर डेªसिंग आदि का कार्य प्रगति पर है। -- as on 01-May-2024
Physical Peramenters