Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
53W1692 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन, देहरादून की ई पत्रावली सं0 55841 दिनांक 25.01.2024
TS Amount (lakhs) : 122.94 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
122.94
Resanction Cost :
122.94
Tentative Cost :
122.94
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 122.94
Demand : 120.00
Allotment : 50.00
Exp in CFY : 25.63
Total Up to Date Exp : 25.63
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 50 %
Sanction on :
5 months 3 weeks ago
25 Jan 2024
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का कार्य प्रगति पर है। -- as on 29-Jun-2024