Administrative Approval Detail : जिलाधिकारी देहरादून के पत्रांक 2100/जि0यो0-लो0नि0वि0/2025-26 दिनांक 26.06.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
5.00
Resanction Cost :
5.00
Tentative Cost :
5.00
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
5.00
Demand :
2.50
Allotment :
2.50
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Unstarted Work
Sanction on : 1 month 1 week ago
26 Jun 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
0 %
Tentative Completion date on : 7 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य का आगणन गठित किया जा रहा है। -- as on 29-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: