Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.17 | 1.17 | 1.170 | 0 | 0.000 | 0.000 |
54W1029 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 1560(।)/।।।(2)/21-18 (एम0एल0ए0)2017, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 15.06.2021
TS Amount (lakhs) : 86.9 Lacs
Financial Detail
Sanction Cost : 86.90 Lacs
Resanction Cost : 86.90 Lacs
Exp. Upto Last Fy : 59.75 Lacs
For CFY 2024-2025
Remaining : 27.15 Lacs
Demand : 27.15 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 59.75 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
15 Jun 2021
Tentative Completion date:
11 months 4 days ago
15 Jun 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 05-Jul-2023
Physical Peramenters