Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
54W1078 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 3209/।।।(2)/21-17 (एम0एल0ए0)2017, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 27.08.2021
TS Amount (lakhs) : 52.87 Lacs
Financial Detail
Sanction Cost : 52.87 Lacs
Resanction Cost : 52.87 Lacs
Exp. Upto Last Fy : 30.99 Lacs
For CFY 2024-2025
Remaining : 21.88 Lacs
Demand : 21.88 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 30.99 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
2 years 8 months ago
27 Aug 2021
Tentative Completion date:
7 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
रू0 30.21 लाख की धराशि का भुगतान दिनांक 18.11.2021 द्वारा विद्युत विभाग को किया गया है। कार्य प्रगति पर है। -- as on 07-Jun-2022
Physical Peramenters