Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.8 | 2.8 | 2.400 | 0.4 | 0.400 | 0.000 |
54W1154 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 शा0सं0 ।/105439/2023 (ई पत्रावली संख्या-44696) लोक निर्माण अनुभाग- देहरादून, दिनांक 13.03.2023
TS Amount (lakhs) : 871.78 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
871.78
Resanction Cost :
871.78
Tentative Cost :
871.78
Exp. Upto Last Fy : 489.00
For CFY 2024-2025
Remaining : 382.78
Demand : 382.78
Allotment : 170.28
Exp in CFY : 170.28
Total Up to Date Exp : 659.28
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 95 %
Sanction on :
1 year 4 months ago
13 Mar 2023
Tentative Completion date:
1 week 5 days from now
30 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.70 कि0मी0 लम्बाई में सोलिंग, इंटर, टाॅप कोट, बी0एम0/ एस0डी0बी0सी0 एवं नाली का कार्य पूर्ण। अन्य कार्य प्रगति पर है। -- as on 04-Jun-2024
Physical Peramenters