Work Profile Report [54W1214]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 पत्रांक ।/167907/2023 (पत्रावली संख्या 50175), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 08.11.2023
TS Amount (lakhs) : 206.85 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
206.85
Resanction Cost :
206.85
Tentative Cost :
206.85
Exp. Upto Last Fy :
117.57
For CFY 2025-2026
Remaining :
89.28
Demand :
89.28
Allotment :
50.00
Exp in CFY :
49.74
Total Up to Date Exp :
167.31
Work completed
Sanction on : 2 years 1 month ago
08 Nov 2023
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
100 %
Tentative Completion date on : 2 months 21 hours ago
15 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 03-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: