Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 1.2 | 0 |
54W1230 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रांक ।/191506/2024 (पत्रावली संख्या 15554), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 19-02-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 0.96 Lacs
Resanction Cost : 0.96 Lacs
Exp. Upto Last Fy : 0.09 Lacs
For CFY 2024-2025
Remaining : 0.87 Lacs
Demand : 0.87 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.09 Lacs
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
3 months 1 hour ago
19 Feb 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रारम्भ करने की कार्यवाही की जा रही है। -- as on 12-Apr-2024
Physical Peramenters