Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 80 | 80 | 0.000 | 80 | 0.000 | 0.000 |
55W1836 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/140173/2023 PWD2-BUD/1/2023-III-2-Public Works Department
TS Amount (lakhs) : 13.6 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
13.60
Resanction Cost :
13.60
Tentative Cost :
13.60
Exp. Upto Last Fy : 0.12
For CFY 2024-2025
Remaining : 13.48
Demand : 12.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.12
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 70 %
Sanction on :
11 months 3 weeks ago
24 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण के अन्तर्गत डिजाइन, ड्राईंग का कार्य पूर्ण। डिजाइन, ड्राईंग की जी0ए0डी0 उत्तर रेलवे, मुरादाबाद को प्रेशित। अनुमोदन के उपरान्त ही डी0पी0आर0 गठन की कार्यवाही की जायेगी। -- as on 29-Jun-2024
Physical Peramenters