Length of Road [Km] | 0.7 | 0.7 | 0.000 | 0.7 | 0.700 | 0.000 |
55W1904 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O.No. 1/181020/2024 PWD2-BUD/ANBU/28/2023-III-2-Public Works Department-Part(1)
TS Amount (lakhs) : 72.24 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
72.24
Resanction Cost :
72.24
Tentative Cost :
72.24
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 72.14
Demand : 50.00
Allotment : 20.00
Exp in CFY : 12.42
Total Up to Date Exp : 12.52
Construction Started
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 1 %
Sanction on :
6 months 1 week ago
10 Jan 2024
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में है। -- as on 28-Mar-2024